Forums

  •  

  • Canada has backed out of their purchase of JSF, Australia is asking for pricing on more F/A-18E-F's, the USN Navy's version is having a hell of a time catching a wire. They put the pivot point to far forward on the arresting gear, the main mounts depress the wire and the hook skips over the wire before it can catch it. Lockheed is having a hard time treading water on this project. The USAF bought 30+ more production models of a Airplane that's not fully tested..... It will cost trillions of dollars to maintain through its lifetime. It was supposed to be a common platform to reduce costs across three services, but only about 20% of it is common among variants....

    McNamara tried to get the Navy to buy a Navalized version of the F-111 for the same reasons. They told him to stuff it after is failed testing. JSF only has one engine, the Navy hates planes with one engine, if it fails yer in the water, or POW. I have seen F/A-14's, A-6's, EA-6B's all come make it back to a Bingo field, or the boat if need be when one engine failed.

    JM2CW

    Cheers

    Hoss
     
  •  

  • I knew one of the maintenance guys that helped with the development of this plane. He said they wanted to use the same pivot joint as the F-15 uses for its speedbrake for the fuel lines and he told them to get bent. If they did that the plane would burn to the ground. Those joints are prone to developing leaks within 100 hours of use. That's not a lot of time in acft parley.
     

  • Nice vid, thanks Duggy, it sure looks fun to fly.

    Good insights from Mike though, and US_Grant, didn't really turn out to be the intended JSF did it?
     

  • This report was just released.
    WASHINGTON (Reuters) - Lockheed Martin Corp's's new F-35 fighter jet has completed over a third of its planned flight tests, but it is still facing problems with the helmet needed to fly the plane, software development and weapons integration, according to a report by the Pentagon's chief weapons tester.

    The 18-page report, sent to Congress on Friday, included a detailed account of those issues and others, which it said underscored the "lack of maturity" of the $396 billion weapons program, the Pentagon's most expensive ever.

    The program exceeded the number of flight tests and specific system tests planned for 2012 but lagged in some areas due to unresolved problems and newly discovered issues. The program has already completed over 20,000 specific tests of items and capabilities on the plane, but has 39,579 more such tests to go.

    The report highlighted the continued growing pains of the ambitious Lockheed fighter program, which began in 2001 and has been restructured three times in recent years to slow down production and allow more progress on the development program.

    Lockheed is building three different models of the F-35 fighter jet for the U.S. military and eight countries that helped pay for its development: Britain, Canada, Italy, Turkey, Denmark, the Netherlands, Australia and Norway. (TC: all of who are either reducing or canceling their orders for this turkey)

    The Pentagon plans to buy 2,443 of the warplanes in coming decades, although many analysts believe U.S. budget constraints and deficits will eventually reduce that overall number. (by about half, current estimates)

    "The lag in accomplishing the intended 2012 flight testing content defers testing to following years, and in the meantime, will contribute to the program delivering less capability in the production aircraft in the near term," said the report prepared by Michael Gilmore, the Pentagon's director of operational test and evaluation.

    Gilmore said the program remained saddled by a high level of concurrency or overlap between development, production and testing. The Pentagon planned that overlap from the start, but its top weapons buyer, Frank Kendall, last year described that approach as "acquisition malpractice."

    CONDUCTING FLIGHT TESTS

    The report said the program conducted 1,092 flight tests in 2012, 18 percent more than the 927 flight tests planned, running more tests than scheduled for the Marine Corps B-model and the Navy's C-model or carrier variant.

    But it fell short of the flight tests planned for the Air Force's conventional takeoff A-model. That model completed 30 percent less test points than planned due to operating limits on the plane and problems with the weapon bay doors, it said.

    It said flight tests were also limited by problems with the air refueling system, which led to restrictions on all A-model planes and required new instrumentation to isolate the cause.

    The plane's stealthy coatings - which make it nearly invisible to enemy radars - were also peeling off on horizontal tail surfaces due to higher-than-expected temperatures during high-speed, high-altitude flights, the report said. (so the stealth doesn't work, and maintaining it means the airplane can only fly about 40% as often as the airplanes it's supposed to replace)

    The Marine Corps version of the plane flew more than planned but lagged its target for test points by 49 percent due to issues with the weapon bay doors and an engine lift fan needed for that B-model's vertical landings, the report said.

    The lift fan is built by Rolls Royce, a supplier to the engine maker, Pratt & Whitney, a unit of United Technologies Corp.

    The weight of the new plane remained fairly steady over the past year, and the mean time between critical failures increased, but the plane's performance remained below the level expected for this point in the program, the report said.

    The report also cited continuing delays with Lockheed's delivery of software for the new fighter, noting that software packages needed to support flight test were delayed or not complete when delivered.

    It said the complex helmet that integrates data for the pilot from all the plane's sensors was still facing issues, as is a computerized logistics system. (A biiiiig problem - the information the helmet gives the pilot is anywhere from 2-5 seconds delayed from reality - that might not sound like a lot, but it's the difference between flying into a solid object, or another airplane in formation, and not, so you might say it's the difference between life and death for the pilot)

    Weapons integration testing was delayed by a number of factors, including problems with the performance of a radar system and in tracking targets.

    Durability testing of the Marine's B-model had to be halted in December after multiple cracks were found on the underside of the plane's fuselage, the report said.

    It also cited problems with the ability of the Navy's C-model to transfer video and imagery data to ships, and said one live-fire test revealed a potentially serious problem with the coolant system, which was now being addressed. (not to mention it still can't land on a carrier because they forgot to put the tailhook on the tail, something that was first figured out 90 years ago, until the geniuses from Lockheed got involved)

    More work was also needed on a system aimed at protecting the plane from fuel tank explosions caused by lightning, the report concluded, noting that flight operations were currently banned within 25 miles of known lightning conditions.

    No immediate comment was available from Lockheed or the Pentagon's F-35 program office.
     

  • What we need is another Light Weight Fighter program. The last one resulted in the F-16 and the F/A-18 (by way of the YF-17). Build low cost, simple to maintain aircraft for low-intensity wars like Iraq and Afghanistan and build UCAVs like the X-47 for the missions where stealth is needed.
     

Moderator(s): Boelcke, Buhli, cheruskerarmin, Cpt_Farrel, Duggy, Graf, Gumpy, Hayate, HBPencil, HEERDT, Jarink, Jaypack44, Juri_JS, kristorf, mapal, MarcoPegase44, monguse, PatCartier, PIPS, RAF_Loke, Rudi_Jaeger, Tailhook, Tomi_099, US_Grant